Skip to content Skip to footer

Project Hämeenlinna

Phase 1

120 MW

Zoned area

150,000 m²

Ownership

100%

Location

Hämeenlinna, Finland

A data center campus in the MORE Industrial Park in Hämeenlinna, southern Finland — one hour from Helsinki.

Magnora Data Center has since January 2026 developed the project in close dialogue with the City of Hämeenlinna and local stakeholders. The site is zoned for data center use and has received building permit for the data center.

First phase is 120 MW, with plans to develop a significantly larger multi-site campus in the years after. Grid connection is scheduled for Q1 2029, potentially already in H2 2028.

Status

Zoning completed

Building permit secured

Concept design completed

Firm grid connection agreement

LOI for district heating, back-up power and additional electricity

Local stakeholder dialogue

Capacity build-out

Phase 1

120 MW

Phase 2

Up to 250 MW

Phase 3

Additional potential

Location

MORE Industrial Park lies on the E12 with a dedicated junction, midway between Helsinki and Tampere. 4.2 million people live within a two-hour radius.

Helsinki

~100 km

Helsinki-Vantaa airport

~75 km

Tampere

~75 km

E12 motorway

Dedicated junction

People within 100 km

4.2 million

MORE Industrial Park

Southern Finland’s largest business area, with ready-made infrastructure and strong municipal support for industrial development in the area.

1,000+ ha

MORE Industrial Park

100+

Companies in the park

E12

Dedicated junction to the motorway